Anticipated Project Timeline

In Q4 2018, following the completion of environmental studies and assessments, and public and Indigenous engagement, Cascade Power submitted a Facilities Application to the Alberta Utilities Commission and Alberta Environment & Parks. When the Project be approved, construction is anticipated to commence in the spring of 2020, with a planned in-service date of October 2022.